River District:
Sewer installation on NW 9th
& Lovejoy
Weeks of March 1, March 8 & March 15
· 9th
Ave will be restricted to 1 northbound lane.
·
2-way traffic will be maintained on Lovejoy.
·
9th Ave will be closed to southbound
bicycle traffic.
NE Broadway:
Water line installation on Larrabee, Benton & Ross
Week of March 15
· Up to two lanes on the north or south side of Broadway will be closed
during the work hours of 8:30 AM and 6:00 PM.
· Side streets may be closed on either side of Broadway as the work
progresses through the instersections.
· Bicycle access and accommodations will be made on Broadway.
Portland Water Bureau work
on N Wheeler from Broadway to Weidler
Weeks of March 1, March 8 & March 15
Water line installation from
2nd to Williams
Weeks of March 1 & March 8
· Up to two
lanes on the north or south side of Broadway will be closed during the work
hours of 8:30 AM and 6:00 PM.
· Side
streets may be closed on either side of Broadway as the work progresses through
the intersections.
· Bicycle
access and accommodations will be made on Broadway.
Sewer
installation from 2nd to Williams AT NIGHT
Week of March 15
· Up to two
lanes on the north or south side of Broadway will be closed during the work
hours of 11:00PM and 7:00AM.
· Side
streets may be closed on either side of Broadway as the work progresses through
the intersections.
· Bicycle
access and accommodations will be made on Broadway.
Portland Water Bureau work
from 2nd to Williams
Week of March 15
Water work paving from Grand
to 2nd
Week of March 1
· Work is weather dependant
Advanced
Utility work at Grand & MLK
Weeks of March 1, March 8 & March 15
Portland
Water Bureau work at 6th
Week of March 1
N/NE Weidler:
Sewer installation from Ross
to Williams
Weeks of March 1, March 8, & March 15
· Up to two
lanes on the north or south side of Weidler will be closed during the work
hours of 9:00 AM and 6:00 PM.
· Ross may
be closed on either side of Weidler during the work hours of 7:00 AM and 6:00
PM.
· Williams may
be closed on either side of Weidler during the work hours of 7:00 AM and 6:00
PM.
· Bicycle
access will be maintained on Broadway and Weidler with the
following detours:
o Eastbound
bike traffic on N Broadway/Weidler, from Benton to
Williams, will be re-routed onto the sidewalk from 7AM to 4
PM. Bikes must yield to pedestrians on the sidewalk.
o Westbound
bike lane will be closed at times both during the day and night. Bikes will be detoured at Wheeler, one
block north to Dixon and back to Broadway at Benton.
Portland
Water Bureau work from Williams to 6th
Week of March 15
Advanced
Utility work at MLK & Grand
Weeks of March 1, March 8 & March 15
Water line installation at 6th
Weeks of March 1 & March 8
· Up to two lanes on the north or south side of Weidler will be closed
during the work hours of 9:00 AM and 6:00 PM.
· 6th may be closed on either side of Weidler during
construction.
· Bicycle access will be maintained on Weidler.
NE MLK:
Portland Water Bureau crew
work from Irving to Oregon
Week of March 1, March 8 & March 15
Portland Water Bureau crew
work at Davis
Week of March 8
NE Grand:
Advanced
Utility work from Hassalo to Clackamas
Week of March 1
Track installation from Hassalo to Clackamas
Weeks of March 8 & March 15
· Up to two
lanes on the east side of Grand will be closed during the work hours of 9:00 AM
and 6:00 PM.
· Side
streets may be closed east of Grand as the track is installed in the
intersection.
Track installation from
Oregon to Hassalo
Week of March 1
· Up to two
lanes on the east side of Grand will be closed during the work hours of 9:00 AM
and 6:00 PM.
· Side
streets may be closed east of Grand as the track is installed in the
intersection.
Track
installation from Burnside to Davis
Weeks of March 1 & March 8
· Up to two
lanes on the east side of Grand will be closed during the work hours of 9:00 AM
and 6:00 PM.
· Side
streets may be closed east of Grand as the track is installed in the
intersection.
NE 7th Ave:
Portland Water Bureau crew
work at Multnomah
Week of March 1
E Burnside:
Hydrant relocations from 6th
– 12th by Portland Water Bureau Crews (Burnside/Couch Couplet)
Weeks of March 1, March 8
SE MLK:
Sewer installation from Pine
to Washington & 3rd to Grand on Oak
Weeks of March 1, March 8 & March 15
· Oak will
be closed during the work hours of 7:00am and 7:00pm
· Some lane
closures on MLK and Grand may occur as work progresses through the
intersection.
Sewer installation from
Washington to Belmont
Weeks of March 1, March 8 & March 15
· Up to two
lanes on the east or west side of MLK will be closed during the work hours of
7:00am and 3:30pm.
· The two
center lanes on SE MLK may be closed to traffic with the two outside lanes
being the through lanes. Some
locations will have parking closed to accommodate the work in the center of MLK
and ensure it is safe for the crews performing the work.
· Stark may be closed to one lane during the hours of 9:00 AM to 4:30 PM
SE Grand:
Advanced Utility work from
Pine to Burnside
Week of March 8
Track installation from Pine
to Burnside
Week of March 15
· Up to two
lanes on the east side of Grand will be closed during the work hours of 9:00 AM
and 6:00 PM.
· Side
streets may be closed east of Grand as the track is installed in the
intersection.
Water
line installation from Madison to Taylor
Week of March 15
·
Up to two lanes on the east or west side of Grand
will be closed during the work hours of 9:00 AM and 6:00 PM.
Water
line installation from Mill to Madison
Weeks of March 1, March 8 & March 15
· Up to two
lanes on the east or west side of Grand will be closed during the work hours of
9:00 AM and 6:00 PM.
· Bicycle
access will be maintained on Hawthorne.